Micron Clay, NY Construction Progress
Presented by Canaan Realty

Building the Future of Semiconductors in Clay, NY

Live construction progress Β· Updated monthly

Overall Progress 0%

Total Outlook

$100B
Total Investment
$17B
Yearly Economic Impact
2045
Full Operational Capacity
9,000+
Jobs Created

Construction Timeline

In Progress

Heavy Site Clearing & Grading

Jan 2026 – June 2026

Crews are currently on-site staging equipment and clearing the first sections of the 1,400-acre plot. Heavy earth-moving equipment preparing the foundation areas. Utility infrastructure planning and initial installation.

10% Complete
Upcoming

Foundation Work

Q2 2026 – Q2 2027

Deep foundation systems installation. Concrete pouring for primary structures. Underground utilities and infrastructure completion.

Not Started
Upcoming

Structural Framework

Q3 2026 – Q4 2027

Steel framework erected for main fabrication buildings and support facilities. Structural elements assembled and secured.

Not Started
Upcoming

Building Envelope & MEP Systems

Q1 2027 – Q4 2028

Exterior walls, roofing, and weather sealing. Installation of mechanical, electrical, and plumbing infrastructure critical for cleanroom operations.

Not Started
Upcoming

Cleanroom Construction

Q1 2028 – Q2 2029

Installation of advanced cleanroom environments with precision air filtration, contamination control, and specialized flooring systems.

Not Started
Upcoming

Equipment Installation

Q3 2029 – Q2 2030

Delivery and installation of advanced semiconductor manufacturing equipment. Testing and calibration of production systems.

Not Started
Upcoming

Commissioning & Production Ramp

Q3 2030 – 2041

System commissioning, test production runs, and gradual ramp-up to full manufacturing capacity. Training and certification of operations staff. First production expected in late 2030. The full site buildout (all four fabs) is scheduled to continue through 2041, with full operational capacity reached by 2045.

Not Started

Monthly Updates

πŸ“…
Feb 2026
πŸ“…
Jan 2026
February 2026

Current Activity

  • Active Mass Grading: Heavy earth-moving equipment is now actively reshaping the 1,400-acre White Pine Commerce Park site
  • Wetland Mitigation Launch: Work has begun on the mandated environmental offsets, including the creation of bat habitats and sediment control systems
  • Infrastructure Staging: Temporary power and construction water lines are being extended to the site perimeter to support the 4,200 workers expected at peak
  • Mobilization Phase: Contractor Gilbane has established the primary on-site construction offices and logistics hubs
  • Legal/Compliance: Monitoring ongoing environmental litigation (Jobs to Move America lawsuit) to ensure no work stoppages occur
What’s Next
Q2 2026 Milestone: Transition from site clearing to the first major concrete pours for the Fab 1 foundation. Utility Expansion: Ongoing upgrades to the local Syracuse water and sewer infrastructure to handle the 20 million gallons per day required by the plant.